Liversuch industries uses a kanban system to manage production of the J-15 sub-assembly. They have an hourly demand for

Posted: Wed Jul 06, 2022 6:05 am
by answerhappygod
Liversuch industries uses a kanban system to manage productionof the J-15 sub-assembly. They have an hourly demand for 250 unitsand use containers that hold 50 units each. It takes 90 minutes tofill and move a container of parts to the right place on the J-15line that is currently rated at a 20% safety factor. How manyproduction cards are needed?