Page 1 of 1

Consider the following work breakdown structure: What is the estimated expected (mean) time for project completion? Time

Posted: Wed Jul 06, 2022 6:03 am
by answerhappygod
Consider The Following Work Breakdown Structure What Is The Estimated Expected Mean Time For Project Completion Time 1
Consider The Following Work Breakdown Structure What Is The Estimated Expected Mean Time For Project Completion Time 1 (14.52 KiB) Viewed 20 times
Consider the following work breakdown structure: What is the estimated expected (mean) time for project completion? Time Estimates (days) Most Likely Activity Start A BUA В с D E F Precedes A, B C, D D E F F End Optimistic 44 45 42 31 27 58 50 60 45 40 36 70 Pessimistic 56 75 48 49 39 82