a) Create a Work Breakdown Structure (WBS) that lists all the steps to complete the project based on this project schedu
Posted: Tue Jul 05, 2022 1:37 pm
a) Create a Work Breakdown Structure (WBS) that lists all thesteps to completethe project based on this project schedule:
Task
Description
Duration (Days)
Predecessor Tasks
A
Project initiation
1
-
B
Determine user requirements
3
A
C
Feasibility analysis
4
A
D
Management presentation
1
B, C
E
System design
3
D
F
Development
14
E
G
Test system
5
F
H
Deployment
1
G
WBS can be hand-drawn or using asuitable software application.
b) Develop PERT/CPM chart explaining the early and late startfor each task. Identify the critical path and the total time tofinish the project based on this project schedule. PERT/CPM chartmust be created using a suitable software application such asdraw.io.
Task
Description
Duration (Days)
Predecessor Tasks
A
Project initiation
1
-
B
Determine user requirements
3
A
C
Feasibility analysis
4
A
D
Management presentation
1
B, C
E
System design
3
D
F
Development
14
E
G
Test system
5
F
H
Deployment
1
G
WBS can be hand-drawn or using asuitable software application.
b) Develop PERT/CPM chart explaining the early and late startfor each task. Identify the critical path and the total time tofinish the project based on this project schedule. PERT/CPM chartmust be created using a suitable software application such asdraw.io.