Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology
Posted: Tue Jul 05, 2022 11:42 am
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) ABCDEFG 423∞0 63 4 8 Crash Time (weeks) 3 1 3 4 3 2 2 Normal Cost $2,000 $2,100 $600 $2,500 $900 $3,000 $1,500 Total Cost with Immediate Crashing Predecessor(s) $2,700 $2,900 $600 $2,800 $1,275 $4,200 $2,000 a) Based on the given information regarding the activities for the project, the project length = A B с D, E weeks.