Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to fi
Posted: Sun Jul 03, 2022 5:23 pm
8. Enter ES and LF of the following activities: ES of activity Dis:= ES of activity F is := LF of activity G is := LF of activity C is := 9. Enter the slack of the following activities: The slack time for activity G is := The slack time for activity E is := 10. The project length is := 11. What is (are) the critical path(s)? Enter 1, if your answer is A-B-E-F Enter 2, if your answer is A-B-D-F Enter 3, if your answer is A-C-D-F Enter 4, if your answer is A-B-D-F and A-C-G Enter 5, if your answer is A-B-E-F and A-C-G Answer: