5. What is (are) the critical path(s)? Enter 1 if your answer is A-D-G Enter 2 if your answer is B-D-G Enter 3 if your a
Posted: Sun Jul 03, 2022 5:23 pm
5. What is (are) the critical path(s)? Enter 1 if your answer is A-D-G Enter 2 if your answer is B-D-G Enter 3 if your answer is B-E-G Enter 4 if your answer is A-B-E-G Enter 5 if your answer is B-E-G and C-F-H Answer: Activity 6. What is the project length? Answer: 13. 7. What is the slack of the shortest path? Answer: ABCDE I F G H 0 Immediate Activity Time Predecessor A, B B с D, E FL 3 2 3 6 3 1