Incorrect Question 2 Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of

Posted: Sun Jul 03, 2022 5:23 pm
by answerhappygod
Incorrect Question 2 Process A Has Fixed Costs Of 1000 And Variable Costs Of 5 Per Unit Process B Has Fixed Costs Of 1
Incorrect Question 2 Process A Has Fixed Costs Of 1000 And Variable Costs Of 5 Per Unit Process B Has Fixed Costs Of 1 (23 KiB) Viewed 15 times
Incorrect Question 2 Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of $500 and variable costs of $15 per unit. What is the crossover point between process A and process B? If we need to manufacture 75 units, which Process should we choose? Crossover at 200 units, pick process B Crossover at 50 units pick process A Crossover at 50 units, pick process B Crossover is at fixed cost of $500 for quantity of 75 units 0/1 pts Crossover at 33 units pick process A