Page 1 of 1

Question 26 Which one of the following statements concerning Master Production Schedule (MPS) is INCORRECT? O MPS quanti

Posted: Sun Jul 03, 2022 5:22 pm
by answerhappygod
Question 26 Which One Of The Following Statements Concerning Master Production Schedule Mps Is Incorrect O Mps Quanti 1
Question 26 Which One Of The Following Statements Concerning Master Production Schedule Mps Is Incorrect O Mps Quanti 1 (251.8 KiB) Viewed 13 times
Question 26 Which One Of The Following Statements Concerning Master Production Schedule Mps Is Incorrect O Mps Quanti 2
Question 26 Which One Of The Following Statements Concerning Master Production Schedule Mps Is Incorrect O Mps Quanti 2 (179.34 KiB) Viewed 13 times
Question 26 Which One Of The Following Statements Concerning Master Production Schedule Mps Is Incorrect O Mps Quanti 3
Question 26 Which One Of The Following Statements Concerning Master Production Schedule Mps Is Incorrect O Mps Quanti 3 (253.57 KiB) Viewed 13 times
Question 26 Which one of the following statements concerning Master Production Schedule (MPS) is INCORRECT? O MPS quantity represents production, not demand. MPS details the recipe structure of all components going into a product.. O MPS shows what needs to be produced, not what can be produced. O MPS may or may not be about finished products. O MPS consists of customer orders and forecasts.

Question 25 Which one of the following reasons does NOT cause scheduling difficulties? O It is an ongoing task. O Setup time variability. O Fixed process times. O Set of jobs may vary. It is not an exact science.

Question 23 Short-term schedules are prepared O Directly from the aggregate plans O Directly from the capacity plans O From the purchasing plans O From inventory records for items that have been used up From master schedules which are derived from aggregate plans