Transmissions are delivered to the fabrication line three at a time. It takes two hours for transmissions to be delivere

Posted: Sun Jul 03, 2022 5:22 pm
by answerhappygod
Transmissions Are Delivered To The Fabrication Line Three At A Time It Takes Two Hours For Transmissions To Be Delivere 1
Transmissions Are Delivered To The Fabrication Line Three At A Time It Takes Two Hours For Transmissions To Be Delivere 1 (12.1 KiB) Viewed 13 times
Transmissions are delivered to the fabrication line three at a time. It takes two hours for transmissions to be delivered. Approximately five vehicles are produced each hour, and management has decided that 20 percent of expected demand should be maintained as safety stock. How many kanban card sets are needed? (Round up your answer to the next whole number.) Number of kanban card sets