Exercise 3: Questions 1. Draw AOA or AON to find the paths 2. Draw a Gantt chart 3. You want to crash the duration by 5

Posted: Sun Jul 03, 2022 4:26 pm
by answerhappygod

[The extension bmp has been deactivated and can no longer be displayed.]

[The extension bmp has been deactivated and can no longer be displayed.]

Exercise 3: Questions 1. Draw AOA or AON to find the paths 2. Draw a Gantt chart 3. You want to crash the duration by 5 days, how much will be the cost? 4. Show resource levelling, first by drawing loading table.

Exercise 3: Activity Predecessor Duration Resource A B с D E F G H I J A B B C,D C,D C,D,E C,D,E H,F 2 3 2 3 2 3 2 7 5 Сл LO 6 4 4 2 3 3 3 1 5 4 4 Crash Days 1 2 1 0 1 1 3 2 4 Crash Cost 100 200 100 0 300 350 150 120 250 110