Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like

Posted: Sun Jul 03, 2022 4:16 pm
by answerhappygod
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like 1
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like 1 (21.22 KiB) Viewed 10 times
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B с D Time (weeks) 5 6 2 2 Immediate Predecessor(s) A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A B с Activity E F G H ES 0 0 Time (weeks) 3 6 9 8 EF 5 6 7 Immediate Predecessor(s) B B C, E D, F