The following represents a project with known activity times. All times are in weeks. Find a critical path by drawing PE
Posted: Sun Jul 03, 2022 3:17 pm
The following represents a project with known activity times.All timesare in weeks.
Find a critical path by drawing PERT chart indicating activity,time, ES, EF, LS, LF in each ofthe node that shows in the class note.