Page 1 of 1

4. A city hall plans on holding a townhall event at the end of the Fall. The activities that have to be completed, durat

Posted: Sun Jul 03, 2022 3:17 pm
by answerhappygod
4.
A city hall plans on holding a townhall event at the end of theFall. The activities that have to be completed, duration of eachactivity, and their sequence are listed in the table below:
a. Determine the project duration.
b. What is the earliest start, earliestfinish time, latest start, latest finish time for activity E?
5.
A node has one entering activity, a, and two leaving activities,b and c. Given the following information, determine the lateststarting time for activity a: EFb = 15, EFc = 17, LFb = 24, LFc =27; activity times are a = 4, b = 6, c = 8.