A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and the
Posted: Sun Jul 03, 2022 3:17 pm
company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below: Activity Break down both machines. Clean machine 1 Clean machine 2 Re-set machine 1 Re-set machine 2 Re-calibrate both machines Final test Designation A B C D E F G Immediate Predecessor None A A B с D and E F Time in Days 3 3 3 1 2 1 2 Using the Single Time Estimate CPM procedure, what is the critical path for the project & the overall project duration? OA. ACEFG & 11 days OB. ACEFG & 10 days OC. ABDFG & 10 days O D. ABDFG & 11 days. O E. ABCDG & 10 days
A