A company must perform a maintenance project consisting of eight activities. The activities, their predecessors, and the

Posted: Sun Jul 03, 2022 3:17 pm
by answerhappygod
A Company Must Perform A Maintenance Project Consisting Of Eight Activities The Activities Their Predecessors And The 1
A Company Must Perform A Maintenance Project Consisting Of Eight Activities The Activities Their Predecessors And The 1 (48.75 KiB) Viewed 10 times
A company must perform a maintenance project consisting of eight activities. The activities, their predecessors, and their respective time estimates are presented below: Time in Days Activity Designation Break down both machines Setup machine 1 Setup machine 2 Clean machine 1 Clean machine 2 Re-set machine 1 Re-set machine 2 Re-calibrate both machines Final test A B с D E F G H 1 Immediate Predecessor None A A B с E F. G H Using the Single Time Estimate CPM procedure, what is the slack time for activity F? O A. 1 day OB. 2 days O C. 3 days O D.0 days 3 1 2 3 3 4 2 1 2