Sammy’s company contract to repair, recondition, and refurbish commercial and industrial icemakers from restaurants, sea

Posted: Sun Jul 03, 2022 1:31 pm
by answerhappygod
Sammy’s company contract to repair, recondition, and refurbishcommercial and industrial icemakers from restaurants, seafoodprocessors, and similar organizations. He currently has five jobsto be scheduled, shown in the order in which they arrived. JobProcessing Time (hours) Due (hours) V 20 50 W 10 35 X 50 90 Y 15 35Z 55 75 a. Construct this table in your answering area to answerthis question (Show your supporting calculations below) (9 marks):Dispatching Rule Job Sequence Average Flow Time Average Number ofJobs Average Lateness FCFS SPT EDD (b) Which dispatching rule hasthe best score for lateness? (1 mark)