YEAR PROJECT A PROJECT B 0 - 15000 - 15000 1 5000 6500 4000 3000 3 6000 5000 4 3000 5000 5 7000 8000 Use the table above
Posted: Wed Apr 06, 2022 9:01 am
YEAR PROJECT A PROJECT B 0 - 15000 - 15000 1 5000 6500 4000 3000 3 6000 5000 4 3000 5000 5 7000 8000 Use the table above to calculate NPV (Net Present Value) , IRR( Internal Rate of Return) and payback period for each project at a discount rate of 12%.And which project will be preferred.