For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete th
Posted: Sun Jul 03, 2022 12:26 pm
For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Use Microsoft Excel. DO NOT use any scheduling software. Activity Duration IPA A BCDE 3 F G H 1 K L M 10 10 8 4 7 10 6 8 15 10 5532 A B A C,D OUFO D C D F H J. G 1 J.K Lag/ Lead -3 2 2 ES EF LS A LF TF