The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durat

Posted: Fri Jul 01, 2022 9:10 am
by answerhappygod
The Following Is A Table Of Activities Associated With A Project At Rafay Ishfaq S Software Firm In Chicago Their Durat 1
The Following Is A Table Of Activities Associated With A Project At Rafay Ishfaq S Software Firm In Chicago Their Durat 1 (14.59 KiB) Viewed 48 times
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) Activity A (start) B C E F (end) 1 7 2 4 3 This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c) The total project completion time for Rafay Ishfaq's software firm is weeks. (Enter your response as a whole number.) Precedes B,C FEE