☐ 6 . b. D Anvils Works' requires, on average, 3,000 tons of aluminum each week, with a standard deviation of 700 tons.

Posted: Fri Jul 01, 2022 9:08 am
by answerhappygod
6 B D Anvils Works Requires On Average 3 000 Tons Of Aluminum Each Week With A Standard Deviation Of 700 Tons 1
6 B D Anvils Works Requires On Average 3 000 Tons Of Aluminum Each Week With A Standard Deviation Of 700 Tons 1 (110.15 KiB) Viewed 35 times
☐ 6 . b. D Anvils Works' requires, on average, 3,000 tons of aluminum each week, with a standard deviation of 700 tons. The lead time to receive its orders is 10 weeks. The holding cost for one ton of aluminum for one week is $10. It operates with a 0.98 in-stock probability. Use Table 11.5. D C. d. ☐e. a. On average, how many tons does it have on order? (Round your answer to nearest integer.) On average, how many tons does it have on hand? ANSWER (Round your answer to nearest integer.) If its average inventory was 4,500 tons, what would be its average holding cost per week? +/-1 ANSWER (Round your answer to 2 decimal places.) If its average inventory was 12,000 tons, what would be its average holding cost per ton of aluminum? ANSWER (Round your answer to 4 decimal places.) Suppose its on-hand inventory is 5,175 tons, on average. What in-stock probability does it offer to its customers? ANSWER ton S -19 tons 0 per week 4 per ton +/-0.