.. • 16.7 Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of t

Posted: Fri Jul 01, 2022 9:08 am
by answerhappygod
16 7 Maggie Moylan Motorcycle Corp Uses Kanbans To Support Its Transmission Assembly Line Determine The Size Of T 1
16 7 Maggie Moylan Motorcycle Corp Uses Kanbans To Support Its Transmission Assembly Line Determine The Size Of T 1 (33.54 KiB) Viewed 105 times
.. • 16.7 Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kan- ban for the mainshaft assembly and the number of kanbans needed. Setup cost $20 Annual holding cost of mainshaft assembly = $250 per unit Daily production 300 mainshafts = Annual usage = 20,000 (= 50 weeks X 5 days each X daily usage of 80 mainshafts) 3 days Safety stockday's production of mainshafts PX Lead time =