A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28

Posted: Fri Jul 01, 2022 9:05 am
by answerhappygod
A project has four activities: A, B, C, and D. The budgeted(planned) cost of each activity is $22K, $14K, $12K, and $28K,respectively. The planned percentages complete for the current dateare 90%, 80%, 70%, and 20% respectively. The actual percentagescomplete for the current date are 100%, 90%, 75%, and 10%respectively. The actual cost of the work performed to date is$40K. What is the BCWS for Activity A?
Multiple Choice $0 − $5K
$5.01K − $10K
$15.01K − $20K