Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching board assembly lines. Determi
Posted: Fri Jul 01, 2022 9:05 am
Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed Setup cost Annual holding cost Daily production Annual usage Lead time Safety stock $30 $120 per subassembly 40 subassemblies 2.500 (50 weeks x5 days each x daily usage of 10 subassemblies) 12 days 3 days' production Kanban container size units (round your response to the nearest whole number) Number of kanbans needed kanbans (round your response to the nearest whole number.