1. A new product development project has four levels in the work breakdown structure and has been sequenced using a netw
Posted: Fri Jul 01, 2022 9:04 am
1. A new product development project has four levels in the work breakdown structure and has been sequenced using a network diagram. The duration of work packages have been received. What should be done NEXT? (Single choice: 1 out of 4; 2 points) 1. A. Ask for more budget B. Begin with the work breakdown structure C. Finalise the cost estimation D. Finalise the schedule