Page 1 of 1

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine Fletcher would like t

Posted: Fri Jul 01, 2022 9:01 am
by answerhappygod
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like T 1
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like T 1 (7.79 KiB) Viewed 32 times
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like T 2
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like T 2 (20.59 KiB) Viewed 32 times
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like T 3
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like T 3 (25.26 KiB) Viewed 32 times
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like T 4
Dave Fletcher Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine Fletcher Would Like T 4 (45.26 KiB) Viewed 32 times
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the citical path should also be determined. Here are the activity mes Time Activity (weeks) 5 6 2 3 8 C D Immediate Time Predecessoris) Activity (weeks) F G H 5 W 7 Immediate Predecessor(s) B CE D.F
Dave's earliest start (ES) and earliest finish (EF) are: Time Activity (weeks) ABCD А с 5623 Immediate Predecessor(s) A Activity ABCDE I F H Timel Activity (weeks) EFGH ES --- 5597 EF = 7 20 18 Immediate Predecessor(s) B B C, E D.F
Dave's latest start (LS) and latest finish (LF) are: The slack times are: Activity H G OF EDUA 10 90 с А ABCDEFO I А LS 13 11 Activity Slack G H 8 6 10 4 LF
The activities on the critical path are B-E-G A-D-H B-F-H A-C-G The total project completion time for Dave = weeks.