D 1 2 3 4 5 6 7 8 0 Task Mode ✰ ✰ ✰ ✦ ✰ ✰ Task Name Activity 1 activity 2 Activity 3 activity 4 Activity 5 Activity 6 Ac
Posted: Fri Jul 01, 2022 9:00 am
2. Bjorn and Thor are plumbers who have been scheduled to work on the construction of a new school building. Just before the start of the project, Bjorn broke his arm and cannot work on the project. Now Thor has to handle his own activities as well as Bjorn's. Level the project Gantt chart so that Thor is responsible for activities 3, 4, 6, and 7. What is the new estimated completion date for the project?