Question 9 (5 Marks) A contract is under consideration which would require 1,400 hours of direct labour. There is spare

Posted: Fri Jul 01, 2022 8:20 am
by answerhappygod
Question 9 5 Marks A Contract Is Under Consideration Which Would Require 1 400 Hours Of Direct Labour There Is Spare 1
Question 9 5 Marks A Contract Is Under Consideration Which Would Require 1 400 Hours Of Direct Labour There Is Spare 1 (130.57 KiB) Viewed 38 times
Question 9 (5 Marks) A contract is under consideration which would require 1,400 hours of direct labour. There is spare capacity of 500 hours of direct labour, due to the cancellation of another order by a customer. The other time would have to be found by asking employees to work in the evenings and at weekends, which would be paid at 50% above the normal hourly rate of R15. Alternatively, the additional hours could be found by switching labour from other work which earns a contribution of R5 per hour. Required: Calculate the relevant cost of direct labour if the contract is accepted and undertaken.