2 SULIT (c) According to Figure B1(a) & Figure B1(b), calculate the cost of the building using the Cubic Content Method.
Posted: Fri Jul 01, 2022 7:22 am
2 SULIT (c) According to Figure B1(a) & Figure B1(b), calculate the cost of the building using the Cubic Content Method. The price rate given is RM 525.00/m³. Berdasarkan kepada Rajah B1(a) & Rajah B1(b), kirakan kos bangunan dengan menggunakan Kaedah Isipadu Bangunan. Kadar harga yang diberikan adalah RM 525.00/m³. 225 1.80m 11.20 m Area A 18 thick brickwall Ground Level Note: Full pitch Rasfubare the roof Area is usable space. Bumbung curam pernah dimana ruang kumbang adalah ruang yang boleh digunakan Tank Full pitch roof section DCC2073: CONTRACT AND ESTIMATING. 3.80 m Figure B1(a): Floor Plan/ Rajah B1(a): Plan Lantai Area B 45¹ 5 2500 mm 7500 mm T=2.10m [10 marks] [10 markah] H=3.50 m Figure B1(b): Cross Section /Rajah B1(a): Keratan SULIT