2 (b) Based on the information in Table B1(a), calculate the cost of construction for a new hostel building to accommoda
Posted: Fri Jul 01, 2022 7:22 am
2 (b) Based on the information in Table B1(a), calculate the cost of construction for a new hostel building to accommodate about 3,200 students in 2016 consider cost of the materials increased 5% per annum. Berdasarkan maklumat dalam Jadual B1(a), kira kos bagi pembinaan bangunan asrama baru untuk menampung kira-kira 3,200 pelajar pada 2016 dengan mengambilkira kos bahan binaan meningkat sebanyak 5% setahun. Type of Hostel/Jenis Asrama Hostel A Hostel B Hostel C Table B1(a): Type of Hostel and construction cost / Jadual B1(a): Jenis Asrama dan kos pembinaan Construction cost (RM) in Year 2014/Kos pembinaan (RM) dalam tahun 2014 3,000,000.00 2,500,000.00 2,450,000.00 Number of students/Bilangam pelajar 1650 1500 1300 Increase in labour salary (2014-2016) 2% [10 marks] [10 markah]