(b) Based on Figure B4(a), carry out taking off quantities for : Merujuk kepada Rajah B4(a), sediakan pengukuran kuantit
Posted: Fri Jul 01, 2022 7:22 am
(b) Based on Figure B4(a), carry out taking off quantities for : Merujuk kepada Rajah B4(a), sediakan pengukuran kuantiti bagi: i. Formwork for ground beam / kotakbentuk untuk rasuk bumi ii. Reinforcement in ground beam as stirrup/pengikat tetulang dalam rasuk Given: Diberi: i. Concrete cover / Penutup konkrit 40mm ii. Concrete Grade /Grade konkrit 25 iii. No of Ground Beam / Bilangan rasuk bumi = 4 nos. 4Y12 R6-300mm c/c 40 silk KââââI 150 > 500 SECTION OF GROUND BEAM (not to scale) columu size 300mm x 300mm column stump 4Y12 7200 R6-300mm c/c 11 25mm lean concrete Figure B4(a)/Rajah B4(a) colun: column stun SULIT