Consider the following job table with 6 jobs with job completion requirement. Assume a real-time system using EDF (Earli

Posted: Fri Jul 01, 2022 5:38 am
by answerhappygod
Consider The Following Job Table With 6 Jobs With Job Completion Requirement Assume A Real Time System Using Edf Earli 1
Consider The Following Job Table With 6 Jobs With Job Completion Requirement Assume A Real Time System Using Edf Earli 1 (34.07 KiB) Viewed 31 times
Consider the following job table with 6 jobs with job completion requirement. Assume a real-time system using EDF (Earliest Deadline First) processor scheduling. Jobs A B с D Jobs A B с Arrival Time 0 0 1 D E F Run (CPU) Time 3 1 6 2 1 2 E 3 7 17 F 6 5 16 Draw a diagram showing the list of jobs in the order of execution with start time and finish time of each job specified. Identify the jobs that fail to meet their deadline. Further, fill in the following table with start times and finish times of each job. Start Time Deadline 4 1 40 Finish Time