5 The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their dur
Posted: Thu Jun 30, 2022 7:39 pm
5 The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity A (start) B C E F (end) Duration (weeks) 2 2 6 2 4 Precedes B, C E F F Jank Amincia. Suppose that Rafay is only given 9 weeks (instead of 12) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity What is the total crashing cost? $ (Enter your response as a whole number.) A B CEF Crash Cost/Week с $380 $130 $220 $140 $450 Each Activity Should be Reduced BY (weeks) week(s) week(s) week(s) week(s) week(s)