Assuming that the GC is on a GMP contract, and they prefer to keep GCs and GRs separate, for each of the following, indi

Posted: Wed Mar 30, 2022 9:09 am
by answerhappygod
Assuming that the GC is on a GMP contract, and they
prefer to keep GCs and GRs separate, for each of the following,
indicate whether those costs should be included in General
Conditions, General Requirements, or
Neither/Overhead.


Project Manager
Material Hoist
Human Resources Professional
Temporary Power Consumption
Temporary Toilets