Q1. Analyze the given table below to fine the estimated time and the critical path of the project. (Critical path: 5 Mar

Posted: Mon Mar 21, 2022 4:49 pm
by answerhappygod
Q1 Analyze The Given Table Below To Fine The Estimated Time And The Critical Path Of The Project Critical Path 5 Mar 1
Q1 Analyze The Given Table Below To Fine The Estimated Time And The Critical Path Of The Project Critical Path 5 Mar 1 (61.83 KiB) Viewed 48 times
Q1 Analyze The Given Table Below To Fine The Estimated Time And The Critical Path Of The Project Critical Path 5 Mar 2
Q1 Analyze The Given Table Below To Fine The Estimated Time And The Critical Path Of The Project Critical Path 5 Mar 2 (61.83 KiB) Viewed 48 times
Q1. Analyze the given table below to fine the estimated time and the critical path of the project. (Critical path: 5 Marks; Estimated time for completion: 5 Marks=10 Marks) Activities Predecessors Time (days) A - 10 B A 20 с B 5 С 10 E 20 DAI F 15 D, G, H A CF A G 5 H 15 ALLA