Q1. Based on the table below, solve the questions (1-4). (12 Marks) Activity Predecessor Optimistic Most Likely Pessimis

Posted: Tue Sep 07, 2021 7:10 am
by answerhappygod
Q1 Based On The Table Below Solve The Questions 1 4 12 Marks Activity Predecessor Optimistic Most Likely Pessimis 1
Q1 Based On The Table Below Solve The Questions 1 4 12 Marks Activity Predecessor Optimistic Most Likely Pessimis 1 (40.57 KiB) Viewed 106 times
Q1. Based on the table below, solve the questions (1-4). (12 Marks) Activity Predecessor Optimistic Most Likely Pessimistic Duration Duration Duration A 2 4 10 B A 5 8 15 H B 1 2 3 с H 4 10 12 D B 7 9 E с 11 14 21 F DE 9 13 17 G E,F 2 5 7 an- + + 1. What is the probability that the project finishes in less than 40 days. 2. What is the probability that the Activity "G" finishes between 3 and 5 days. 3. Estimate project completion date with at least a 96% confidence level. 4. What is the probability that node "D" has a float more than Zero.