PERT-CPM Formulate the LP considering the Expected Time. Consider a project involving the following activities and prece

Posted: Sat Mar 19, 2022 6:01 pm
by answerhappygod
Pert Cpm Formulate The Lp Considering The Expected Time Consider A Project Involving The Following Activities And Prece 1
Pert Cpm Formulate The Lp Considering The Expected Time Consider A Project Involving The Following Activities And Prece 1 (30.71 KiB) Viewed 34 times
PERT-CPM Formulate the LP considering the Expected Time. Consider a project involving the following activities and precedence relationship. Draw the AON and AOA Diagram then formulate LP model before crashing. Activity Predecessors Expected Time А 4 B 3 с 3 D С 2 E A, B, DN 1 F A, B, D 2 G E, F 3 H A, B, D 3 1 H S J G 2 K G 4 L I, JK 3