PERT-CPM Formulate the LP considering the Expected Time. Consider a project involving the following activities and prece
Posted: Sat Mar 19, 2022 6:00 pm
PERT-CPM Formulate the LP considering the Expected Time. Consider a project involving the following activities and precedence relationship. Draw the AON and AOA Diagram then formulate LP model before crashing. Activity Predecessors Expected Time A 4 B 3 с 3 D С 2 E 1 F A, B, D 2 G EF 3 H A, B, D 3 I H 5 J G 2 K G 4 L IJK 3 A, B, DN الا انا يا الله في كل لي