2. Find the payback period for the given project A and B. Years Project A Project B 0 -700 -500 1 -200 -100 2 100 300
Posted: Wed Mar 16, 2022 9:12 am
2. Find the payback period for the given
project A and B.
Years
Project A
Project B
0
-700
-500
1
-200
-100
2
100
300
3
300
400
4
500
600
a) Draw the chart in a graph sheet and
find payback period for each Project.(4marks=2marks for each
chart)
b) Which project ( Project A or Project
B) your company will choose? Justify your answer. (3marks)