SOLVE AND GRAPH THE PROBLEM The Philippine Institute of Industrial Engineers (PIIE) is planning to put up its own buildi

Posted: Wed Mar 09, 2022 8:31 am
by answerhappygod
SOLVE AND GRAPH THE PROBLEM
The Philippine Institute of Industrial Engineers (PIIE) is
planning to put up its own building. Two proposals being considered
are: A. The construction of the building now to cost P400,000 B.
The construction of a smaller building now to cost P300,000 and at
the end of 5 years, an extension to be added to cost P200,000 By
how much is proposal B more economical than proposal A if interest
rate is 20% and depreciation to be neglected?