A project requires a cash outflow of -$9500 today. In one year, $5044 will be received. In two years, $4619 will be rece

Posted: Fri Mar 04, 2022 9:35 am
by answerhappygod
A project requires a cash outflow of -$9500 today. In one year,
$5044 will be received. In two years, $4619 will be received. In
three years, another $5239 will be received, and in four years,
$7387 will be received.
Given a discount rate of 12%, what is the
NPV?
With formula. Thanks