Given the following information on crash time and crash time per day, what is the cost of crashing the project by 3 days
Posted: Sat Feb 26, 2022 9:08 am
Given the following information on crash time and crash time per day, what is the cost of crashing the project by 3 days? The only critical path is A-C-E-G: Activity Normal time А B ס ס ס ו ד 9 10 5 3 6 3 4 Crash time 8 4 2 2 5 2 2 NNUNNA Crash cost per day 160 50 145 250 184 180 300 E G Your Answer: