A house requires 500 board feet of 2x8 joist material. The joists are to be placed 16" OC. What's the labor cost for fra

Posted: Thu Feb 17, 2022 11:08 am
by answerhappygod
A House Requires 500 Board Feet Of 2x8 Joist Material The Joists Are To Be Placed 16 Oc What S The Labor Cost For Fra 1
A House Requires 500 Board Feet Of 2x8 Joist Material The Joists Are To Be Placed 16 Oc What S The Labor Cost For Fra 1 (35.43 KiB) Viewed 58 times
A house requires 500 board feet of 2x8 joist material. The joists are to be placed 16" OC. What's the labor cost for framing the floor if the workers receive $30.00 per hour? (Round your answer to the nearest dollar.) A. $110 B. $214 C. $150 D. $231