Question 5 (8 marks) The following project has three independent paths as shown in the project network diagram. The dead
Posted: Thu Feb 17, 2022 11:02 am
Question 5 (8 marks) The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. B Activity Optimistic Time (days) Most Likely Time (days) Pessimistic Expected Variance Time Time of (days) (days) Activity 1 HE Start End А 10 16 28 20 B 28 42 C 18 30 42 D 15 15 15 E 1 2 3 F 42 45 48 a) What is the probability that this project will be delayed? Name: b) What is the probability that activity Falone will take between 44 and 46 days?