Page 1 of 1

Question 12 4 Points The daily number of workers that are late for the work on weekdays follows a Poisson distribution w

Posted: Fri Dec 24, 2021 9:56 am
by answerhappygod
Question 12 4 Points The Daily Number Of Workers That Are Late For The Work On Weekdays Follows A Poisson Distribution W 1
Question 12 4 Points The Daily Number Of Workers That Are Late For The Work On Weekdays Follows A Poisson Distribution W 1 (19.58 KiB) Viewed 114 times
Question 12 4 Points The daily number of workers that are late for the work on weekdays follows a Poisson distribution with mean 12. What is the probability of observing 11 or 12 workers are late for the work on a weekday? A. 0.11437 B. 0.22881 C. 0.10943 D. None of the above