5 points Save Answer QUESTION 13 Two alternative structures are considered for a section of road. Plan A uses asphalt pa
Posted: Wed Jun 08, 2022 8:27 am
QUESTION 13 Two alternative structures are considered for a section of road. Plan A uses asphalt pavement; Plan B uses concrete pavement. The first cost of asphalt pavement is $175,000 with an annual maintenance cost of $1,800, and life span of 40 years. The concrete pavement cost is $210,000 with a life of 40 years. Annual maintenance cost of concrete pavement is $1,250. Considering discount rate of 5% per annum and study period of 40 years, which plan do you recommend? (5 marks). For the toolbar, press ALT+F10 (PC) or ALT+FN+F10 (Mac). BIUS Paragraph Open Sans,sa... 10pt A Ix X E :
5 points Save Answer