Focusing on TAKT time, consider the following.
a. You have product demand of 800 units per day. You currently
work one 8-hour shift, with 7.5 real work hours. What is your TAKT
time?
b. Your demand is going up, and you are now at 1,000 units per
day. You have been working overtime. And it is getting expensive.
What is your new TAKT time? Thinking of lean concepts, provide at
least two ideas that might improve your productivity (i.e., reduce
your TAKT time) so that you can reduce overtime.
a. You have product demand of 800 units per day. You currently
work one 8-hour shift, with 7.5 real work hours. What is your TAKT
time?
b. Your demand is going up, and you are now at 1,000 units per
day. You have been working overtime. And it is getting expensive.
What is your new TAKT time? Thinking of lean concepts, provide at
least two ideas that might improve your productivity (i.e., reduce
your TAKT time) so that you can reduce overtime.