The following is a network diagram of the project. 1. Identify the critical path. 2. Assuming the durations are given in
Posted: Mon Jun 06, 2022 7:00 am
The following is a network diagram of the project. 1. Identify the critical path. 2. Assuming the durations are given in days, how long will it take to complete the project? 3. What is the latest start time for activity H? 4. How much slack time do you have to plan the dinner? Plan dinner is Activity "D". International Dinner a-Location Start: Thu 3/31/22 ID: 1 Start: Thu 3/31/22 ID: 2 Finish: Wed 5/4/22 Dur: 25 days Finish: Wed 4/20/2 Dur: 15 days Comp: 0% Res: d-Dinner Start: Thu 3/31/22 ID: 5 Finish: Wed 4/13/2 Dur: 2 wks Res: h-Performances Start: Thu 3/31/22 ID: 9 Finish: Mon 4/11/2 Dur: 8 days Res: b-Furnishings Start: Thu 4/21/22 ID: 3 Finish: Mon 5/2/22 Dur: 8 days Res: c-Decorations Start: Thu 4/21/22 ID: 4 Finish: Tue 4/26/22 Dur: 4 days Res: i-Keynotes Speakers Start: Thu 4/21/22 ID: 10 Finish: Wed 5/4/22 Dur: 2 wks Res: e-Drinks Start: Thu 4/14/22 ID: 6 Finish: Mon 4/18/2 Dur: 3 days Res: g-Music Start: Tue 4/12/22 ID: 8 Finish: Fri 4/15/22 Dur: 4 days Res: f-Dessert Start: Tue 4/19/22 ID: 7 Finish: Thu 4/21/22 Dur: 3 days Res: