Bragg’s Bakery is building a new automated bakery in downtown Omaha. Here are the activities that need to be completed

Posted: Mon Jun 06, 2022 6:22 am
by answerhappygod
Bragg’s Bakery is building a new automated bakery in downtown
Omaha. Here are the activities that need to be completed to
get the new bakery build and the equipment installed. The
Normal Completion Time represents how long it will take to
complete the activity without crashing. The Crash
Completion Time represents how long it will take to complete
the activity if it is crashed.
Activity
Predecessor
Normal Completion Time (Weeks)
Crash Completion Time (Weeks)
Crash (Expediting) Cost/Week
A
--
9
6
$3,000
B
A
8
5
$3,500
C
A
15
10
$4,000
D
B,C
5
3
$2,000
E
C
10
6
$2,500
F
D,E
2
1
$5,000
You must show your work to receive full credit.
c) Bragg’s loses $3,500 in profit per week for every week
the bakery is not completed. How many weeks will the project
take if the bakery is willing to pay the crashing cost as long as
it is economically the right decision?
d) What is the project completion time if all activities are
crashed to their minimum Crash Time? Also, ignoring the
$3,500 lost profit in c), what is the total additional cost
incurred for crashing all of the activities to their minimum Crash
Time compared to the Normal Times?