Homework: Process Selection and Facility Layout Assignment Saved 3 For the set of tasks given below, do the following: T
Posted: Sun Jun 05, 2022 10:34 pm
Homework: Process Selection and Facility Layout Assignment Saved 3 For the set of tasks given below, do the following: Task Task A Immediate Predecessor Time (seconds) 45 11 9 B D 50 26 D 11 12 с 10 T 9 F, G, H J 10 193 Click here for the Excel Data File a. Determine the minimum cycle time and then calculate the cycle time for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) The minimum cycle time seconds The calculated cycle time seconds 3 points Skipped eBook Print