Seved Help Below is the original network diagram for a project. Suppose that after 12 weeks, activities 1-2, 1-3, and 2-
Posted: Sun Jun 05, 2022 10:29 pm
Seved Help Below is the original network diagram for a project. Suppose that after 12 weeks, activities 1-2, 1-3, and 2-4 have been finished; activity 2-5 is 75 percent finished; and activity 3-6 is half finished. How many weeks after the original start time should the project be finished? 10 N 10 Project can be completed in a total of weeks. Save & Exit Submit